Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Girls, women try their hand at marine rescue in Surrey

Achieve Anything Foundation, RCMSAR Crescent Beach host ‘Operation: This IS You! Saving Lives at Sea’

White Rock cadets nab medals at Vernon competition

Thirteen members of 907 Squadron compete at regional meet

Surrey boy living with congenital heart disease to speak at local Tedx event

Mason Vander Ploeg will be speaking on saving the oceans

VIDEO: 2020 BC Winter Games wrap up in Fort St. John as torch passes to Maple Ridge

More than 1,000 athletes competed in the 2020 BC Winter Games

Winds up to 70 km/hr expected across Metro Vancouver

Winds are expected to subside overnight

Still six cases of COVID-19 in B.C. despite reports of Air Canada passenger: ministry

Health ministry wouldn’t comment on specific flight routes

Violent ends to past Indigenous protests haunt Trudeau government

Trudeau adopted a more assertive tone Friday, insisting the barricade must come down

Fraser Health warns some schools of possible COVID-19 exposure

A sixth COVID-19 patient is a woman in her 30s in the Fraser Health region who recently returned from Iran

High-risk sex offender cuts off ankle bracelet, on the loose in Vancouver: police

Vancouver police said Kirstjon Olson, 38, is a provincial sex offender with 27 court-ordered conditions

HIGHLIGHTS: Day one and two at the 2020 BC Winter Games

Athletes had sunny – but cold – weather to work with in Fort St. John

Most Read

l -->