White Rock pier after it was damaged in the Dec. 20 storm. (Christy Fox photo)

$3 million contract awarded for White Rock Pier repair

First phase of reconstruction expected to be complete by July 31

White Rock council awarded a major contract Monday evening for the reconstruction of the city’s iconic pier.

Council endorsed staff’s recommendation to award the project to PPM Civil Constructors (PPMCC) – low bidder at $3,079,740.

Awarding of the contract sets the clock ticking for a schedule of completion of major repairs by July 31, with re-opening of the pier and re-establishment of the telecommunications link projected for Aug. 31.

Engineering and municipal operations director Jim Gordon told council that work could begin as soon as 10 days following Monday’s decision.

Although Coun. David Chesney moved that consideration of the contract be delayed one week for a special council meeting scheduled for April 15, the rest of council voted down the motion and subsequently approved the contract.

Deputy mayor Scott Kristjanson, filling in for vacationing Mayor Darryl Walker, said he saw no need for an extra delay.

“I think we’ve heard loud and clear from residents, and also from businesses on Marine Drive,” he said. “We’ve promised people that this would be done by the end of August.”

The recommendation for PPMCC noted the company scored highest on evaluation criteria, including the proponent’s experience, qualifications, references, proposed work plan, methodology, proposed schedule and price.

The city received a total of five bids after it issued a request for proposal (RFP) March 1. The highest bid came in at $6.5 million.

The project involves installing 66 new steel pipe piles and replacing 15 timber piles; reconstruction of the failed section of the pier with steel piles and precast concrete substructure; installation of timber decking and handrails; and replacing timber piles in select locations.

The contract awarded Monday evening is only for the damaged section of the pier.

“It’s step one of a much larger project to construct the whole pier,” Gordon said.

In answer to a question from Coun. Helen Fathers, financial services director Sandra Kurylo said that the city estimates that as much as $3.1 million of the initial repair work will be paid by the city’s insurance on the pier.

The work, which includes repair and upgrading of approximately 20 per cent of the pier, is also to include the demolition of damaged components and salvage of the timber planks.

A 100-foot section of the pier was destroyed Dec. 20 after a windstorm aligned with heavy rain and a high tide. The pier and western wharf were destroyed and several rows of piles along the pier sustained impact damage, likely from floating debris, the city document states.

“The December storm illustrated the vulnerability of the Pier to storm surges that could potentially occur more frequently due to climate change,” noted a report to council from Gordon.

“The remaining sections of the Pier are vulnerable to damage from future storms. Over 60 truckloads of large logs and debris were removed from the beach following the December storm. The Pier is not constructed to withstand battering of the wooden pile cap and deck structure with logs or other hard debris during storm surges.”

According to the report, the new pier is to be designed to current building codes; meet environmental standards; be protected against earthquakes; be hardened against debris-laden storm surges; and be able to support an ambulance in the event of a medical emergency.

The remainder of the pier, as highlighted in a Jan. 28 city corporate report, is to be upgraded to modern standards over the next two winter seasons, at initial estimates of some $16 million.

“However, if funding is available and senior government approvals are in place, the restoration of the remainder of the Pier could start this fall. It is likely that this work would take approximately one (1) year to complete with a continuous construction schedule. If contract resources are available and permitting allows for two (2) construction crews to work concurrently, the project could potentially be completed sooner,” the report says.

It also outlines a number of project risks and mitigation measures that come with the reconstruction of the damaged section of the pier.

Impacts to visitor parking is one of the risks, according to the city.

The project has allocated eight parking stalls along the south side of the parking lot west of the museum. This area is to be used for site office, safety trailer and equipment storage. The remainder of the parking lot is to be open to the public.

The RFP specifies a marine contractor so materials can arrive by barge, and if crew parking is required, the city will be directing crews to park at Montecito Parkade.

The West Beach Parkade, located at the corner of Victoria Avenue and Vidal Street and is to be open to the public this month, is to increase parking availability.

The contract includes a liquidation damages clause and performance bonus clause to reduce schedule risks. The pier arches have a minimum of 12 weeks’ lead-time, and will be procured in a separate contract.

The city has been in contact with the Semiahmoo First Nation about the project, and an archeological consultant has been retained to prepare an archeological overview assessment.

The pier is located in Semiahmoo Bay, which is part of the Boundary Bay Wildlife Management Area (WMA) and is regulated under the Wildlife Act. Permits are required for construction work within the WMA, the city agenda states.

The city has retained environmental consultant Hatfield Consultants to provide permitting and environmental-monitoring services.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Provincial COVID-19 data can now be used for B.C. to prepare for a second wave

In the past week, B.C. has seen a slight spike in daily test-positive case counts

PHOTOS: Surrey rally supports Mona Wang, calls for wellness check reform

Security camera footage shows Wang being dragged, stepped on during RCMP wellness check at UBCO

Filming applications ‘coming in slowly’ to the City of Surrey

Netflix cancels ‘Sabrina’, but filming manager says new calls coming in to film in Cloverdale

‘Did anything good come out of my son’s overdose death?’ – South Surrey mom

Maggie Plett says action still needed on recovery homes

COVID-19: Daily update on the pandemic in Surrey, White Rock and beyond

JULY 11: B.C.’s COVID-19 job recovery led by tourism, finance

QUIZ: Are you ready for a summer road trip?

How much do you really know about roads, motor vehicles and car culture? Take this quiz to find out.

Genetic detectives begin work to trace spread of COVID-19 in Canada

The kinds of genetic technology being used for this project did not exist when SARS hit Canada in 2003

B.C. Ferries increasing passenger capacity after COVID-19 restrictions

Transport Canada 50-per-cent limit being phased out, no current plans to provide masks

Once-in-a-lifetime comet photographed soaring over Abbotsford

Photographer Randy Small captures Comet NEOWISE in early-morning sky

Amber Alert for two Quebec girls cancelled after bodies found

Romy Carpentier, 6, Norah Carpentier, 11, and their father, Martin Carpentier, missing since Wednesday

Bringing support to Indigenous students and communities, while fulfilling a dream

Mitacs is a nonprofit organization that operates research and training programs

B.C. man prepares to be first to receive double-hand transplant in Canada

After the surgery, transplant patients face a long recovery

Grocers appear before MPs to explain decision to cut pandemic pay

Executives from three of Canada’s largest grocery chains have defended their decision to end temporary wage increases

Man shot dead in east Abbotsford suburbs

Integrated Homicide Investigative Team called to investigate

Most Read

l -->