White Rock pier after it was damaged in the Dec. 20 storm. (Christy Fox photo)

White Rock pier after it was damaged in the Dec. 20 storm. (Christy Fox photo)

$3 million contract awarded for White Rock Pier repair

First phase of reconstruction expected to be complete by July 31

White Rock council awarded a major contract Monday evening for the reconstruction of the city’s iconic pier.

Council endorsed staff’s recommendation to award the project to PPM Civil Constructors (PPMCC) – low bidder at $3,079,740.

Awarding of the contract sets the clock ticking for a schedule of completion of major repairs by July 31, with re-opening of the pier and re-establishment of the telecommunications link projected for Aug. 31.

Engineering and municipal operations director Jim Gordon told council that work could begin as soon as 10 days following Monday’s decision.

Although Coun. David Chesney moved that consideration of the contract be delayed one week for a special council meeting scheduled for April 15, the rest of council voted down the motion and subsequently approved the contract.

Deputy mayor Scott Kristjanson, filling in for vacationing Mayor Darryl Walker, said he saw no need for an extra delay.

“I think we’ve heard loud and clear from residents, and also from businesses on Marine Drive,” he said. “We’ve promised people that this would be done by the end of August.”

The recommendation for PPMCC noted the company scored highest on evaluation criteria, including the proponent’s experience, qualifications, references, proposed work plan, methodology, proposed schedule and price.

The city received a total of five bids after it issued a request for proposal (RFP) March 1. The highest bid came in at $6.5 million.

The project involves installing 66 new steel pipe piles and replacing 15 timber piles; reconstruction of the failed section of the pier with steel piles and precast concrete substructure; installation of timber decking and handrails; and replacing timber piles in select locations.

The contract awarded Monday evening is only for the damaged section of the pier.

“It’s step one of a much larger project to construct the whole pier,” Gordon said.

In answer to a question from Coun. Helen Fathers, financial services director Sandra Kurylo said that the city estimates that as much as $3.1 million of the initial repair work will be paid by the city’s insurance on the pier.

The work, which includes repair and upgrading of approximately 20 per cent of the pier, is also to include the demolition of damaged components and salvage of the timber planks.

A 100-foot section of the pier was destroyed Dec. 20 after a windstorm aligned with heavy rain and a high tide. The pier and western wharf were destroyed and several rows of piles along the pier sustained impact damage, likely from floating debris, the city document states.

“The December storm illustrated the vulnerability of the Pier to storm surges that could potentially occur more frequently due to climate change,” noted a report to council from Gordon.

“The remaining sections of the Pier are vulnerable to damage from future storms. Over 60 truckloads of large logs and debris were removed from the beach following the December storm. The Pier is not constructed to withstand battering of the wooden pile cap and deck structure with logs or other hard debris during storm surges.”

According to the report, the new pier is to be designed to current building codes; meet environmental standards; be protected against earthquakes; be hardened against debris-laden storm surges; and be able to support an ambulance in the event of a medical emergency.

The remainder of the pier, as highlighted in a Jan. 28 city corporate report, is to be upgraded to modern standards over the next two winter seasons, at initial estimates of some $16 million.

“However, if funding is available and senior government approvals are in place, the restoration of the remainder of the Pier could start this fall. It is likely that this work would take approximately one (1) year to complete with a continuous construction schedule. If contract resources are available and permitting allows for two (2) construction crews to work concurrently, the project could potentially be completed sooner,” the report says.

It also outlines a number of project risks and mitigation measures that come with the reconstruction of the damaged section of the pier.

Impacts to visitor parking is one of the risks, according to the city.

The project has allocated eight parking stalls along the south side of the parking lot west of the museum. This area is to be used for site office, safety trailer and equipment storage. The remainder of the parking lot is to be open to the public.

The RFP specifies a marine contractor so materials can arrive by barge, and if crew parking is required, the city will be directing crews to park at Montecito Parkade.

The West Beach Parkade, located at the corner of Victoria Avenue and Vidal Street and is to be open to the public this month, is to increase parking availability.

The contract includes a liquidation damages clause and performance bonus clause to reduce schedule risks. The pier arches have a minimum of 12 weeks’ lead-time, and will be procured in a separate contract.

The city has been in contact with the Semiahmoo First Nation about the project, and an archeological consultant has been retained to prepare an archeological overview assessment.

The pier is located in Semiahmoo Bay, which is part of the Boundary Bay Wildlife Management Area (WMA) and is regulated under the Wildlife Act. Permits are required for construction work within the WMA, the city agenda states.

The city has retained environmental consultant Hatfield Consultants to provide permitting and environmental-monitoring services.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Family and friends of Hudson Brooks marched as part of a call for answers from an IIO investigation into his 2015 death. (Black Press Media files)
Inquest to look into RCMP shooting death of Hudson Brooks

Charges agains the RCMP officer who shot Brooks were stayed in 2019

A little brown bat, which has become endangered due to white-nose syndrome. (Greg Michalowski photo)
Bat sightings on Semiahmoo Peninsula spark worries of white-nose syndrome

Fungal disease is deadly for local bat populations: BC Community Bat Program

The old Rickshaw sign today, with the former restaurant location in the building behind it. (Photo: Tom Zillich)
SURREY NOW & THEN: Rickshaw sign stands as a reminder of Jung family’s restaurant days

A weekly look back at Surrey-area landmark sites and events

Mike LeSage. (submitted photo)
LeSage to head Community Policing Bureau of new Surrey police force

Second of three Deputy Chief Constables to be hired by fledgling force

White Rock Evergreen Baptist Society had 46 COVID-19 cases as of Jan. 13, according to a recent report released by the province. (Peace Arch News photo)
White Rock care home’s COVID-19 cases jump 50 per cent in a week: report

Three White Rock/South Surrey care facilities among B.C. sites with active outbreaks

An animated Gordie Hogg introduces his 'Community Connections' videos. (YouTube screenshot)
Community Connections: Gordie Hogg speaks with Scott Ackles

Former mayor, MP began posting conversations on YouTube in June

Powell River-Sunshine Coast MLA Nicholas Simons was appointed to the NDP cabinet as minister of social development and poverty reduction after the October 2020 B.C. election. (Hansard TV)
B.C. job training fund increased for developmentally disabled

COVID-19 has affected 1,100 ‘precariously employed’ people

B.C. driver’s licence and identity cards incorporate medical services, but the passport option for land crossings is being phased out. (B.C. government)
B.C. abandons border ID cards built into driver’s licence

$35 option costing ICBC millions as demand dwindles

BC Emergency Health Services has deployed the Major Incident Response Team (MIRRT) as COVID-19 positive cases rise in the Williams Lake region. (Monica Lamb-Yorski photo - Williams Lake Tribune)
B.C.’s rapid response paramedics deployed to Williams Lake as COVID-19 cases climb

BC Emergency Health Services has sent a Major Incident Rapid Response Team to the lakecity

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

(Phil McLachlan - Black Press Media)
RCMP say ice climber seriously injured after reportedly falling 12 metres near Abraham Lake

Police say man’s injuries were serious but not life-threatening

The RCMP was called to a condo complex in Langley City in the early hours of Jan. 18, 2021, for a shooting. (Shane Mackichan/Special to the Langley Advance Times)
27-year-old taken to hospital after overnight targeted shooting in Langley

RCMP have not confirmed the incident is link to the Lower Mainland gang conflict

U.S. military units march in front of the Capitol, Monday, Jan. 18, 2021 in Washington, as they rehearse for President-elect Joe Biden’s inauguration ceremony, which will be held at the Capitol on Wednesday. (AP Photo/J. Scott Applewhite)
Biden aims for unifying speech at daunting moment for U.S.

President Donald Trump won’t be there to hear it

Williams Lake physician Dr. Ivan Scrooby and medical graduate student Vionarica Gusti hold up the COSMIC Bubble Helmet. Both are part of the non-profit organization COSMIC Medical which has come together to develop devices for treating patients with COVID-19. (Monica Lamb-Yorski photo - Williams Lake Tribune)
Group of B.C. doctors, engineers developing ‘bubble helmet’ for COVID-19 patients

The helmet could support several patients at once, says the group

Most Read