Site C dam project design has been changed to eliminate a separate bridge across the Peace River

Site C dam project design has been changed to eliminate a separate bridge across the Peace River

Permits approved for Site C hydro dam

BC Hydro negotiating compensation with aboriginal communities, B.C. cabinet to decide soon whether $8 billion project will go ahead

VICTORIA – Both the federal and provincial governments have issued environmental assessment certificates for BC Hydro’s Site C dam, the proposed third hydroelectric project on the Peace River in northeastern B.C.

The approvals include dozens of legally binding conditions, including a $20 million farmland enhancement fund to offset river bottom land that would be flooded, and compensation for local aboriginal groups whose historic treaty rights to hunting, fishing and trapping would be affected.

Cost of the project, last estimated by BC Hydro at $7.9 billion, will factor into a final decision by the B.C. cabinet whether to go ahead with the dam. Energy Minister Bill Bennett has indicated he expects the final investment decision to be made by the end of 2014, and if it’s approved, work would begin immediately.

Among the 77 B.C. conditions is an aboriginal business participation strategy to share the estimated 10,000 person-years of construction work the dam project would generate.

Seven aboriginal communities affected by the proposal have been offered cash and Crown land to compensate for land lost by construction of the dam. All are signatories to Treaty 8, which ensures their rights to hunt, trap and fish as they did before the treaty was signed in 1899. Officials say five of the seven are currently in negotiations.

Situated near Fort St. John and downstream of the W.A.C. Bennett and Peace Canyon dams, Site C’s 1,050-metre-long earthfill dam would create a reservoir 83 km long and two to three times the current width of the river.

It requires two power lines built in the same corridor as the existing line, and six water turbine generators that would produce enough electricity to power about 450,000 homes.

BC Hydro estimates that because Site C would use water held back in the existing Williston Lake reservoir, it would generate 35 per cent of the energy as the Bennett dam with only five per cent of the reservoir area.

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

A median has been installed at the intersection of 40 Avenue and 176 Street. (Stephanie Cadieux Twitter photo)
Median installed at South Surrey ‘death trap’ intersection

Safety improvements made to 176 Street (Highway 15) at 40 Avenue

(Contributed photo)
PHOTOS: South Surrey Unitarians take call for racial justice to street

‘When we see it in our lives, we can either say something about it or be complicit in it’

Neilson Grove Elementary students water their new cedar tree. As part of its commitment to reconciliation, the Delta School District is planting a cedar tree at every school and district site as a way to show appreciation and respect for local First Nation culture through its Giving Tree Project. (Delta School District photo)
Cedars planted at Delta schools as part of reconciliation

‘Giving Tree Project’ a way to show respect and appreciation for First Nation culture

Surrey Eagles forward Michael Abgrall had two goals and two assists in a pair of weekend victories. (Damon James photo)
Surrey Eagles’ offence soars in pair of lopsided victories

BC Hockey League squad scores 22 goals in two wins over Powell River, Coquitlam

In this image from NASA, NASA’s experimental Mars helicopter Ingenuity lands on the surface of Mars Monday, April 19, 2021. The little 4-pound helicopter rose from the dusty red surface into the thin Martian air Monday, achieving the first powered, controlled flight on another planet. (NASA via AP)
VIDEO: NASA’s Mars helicopter takes flight, 1st for another planet

The $85 million helicopter demo was considered high risk, yet high reward

Carver Ken Sheen had almost finished work on a large cowboy carving commissioned by the City of Williams Lake to replace the original overlooking the Stampede Grounds when fire broke out Friday, April 18 at his property between Williams Lake and Quesnel. (Pine River Carving Facebook photos)
Cow boss statue destined for Williams Lake Stampede Grounds goes up in flames

Carver Ken Sheen lost the statue, all his tools and his shop in the blaze

B.C. Labour Minister Harry Bains. (Hansard TV)
B.C. moves to protect employee pay for COVID-19 vaccination

Most won’t need to take time off work, labour minister says

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Vancouver Police Department. (Black Press Media files)
Abbotsford man named as victim of fatal weekend shooting in Vancouver

Harpreet Dhaliwal, 31, killed outside of Cardero’s restaurant in Coal Harbour

New figures show Canadian housing prices outpacing those in other developed countries. (Black Press Media file photo)
Canadian housing prices fastest rising in the world

Relative to 2000, housing prices have risen by a factor of more than 2.5

Russ Ball (left) and some of the team show off the specimen after they were able to remove it Friday. Photo supplied
80-million-year-old turtle find on B.C. river exciting fossil hunters

Remains of two-foot creature of undetermined species will now make its home at the Royal BC Museum

Large gatherings of people at Kitsilano Beach on Saturday, April 17, 2021. (Walter Wells/Twitter)
Vancouver police to reassess enforcement of COVID rules at outdoor parties: mayor

No tickets were given out for a large outdoor party at Kitsilano Beach

Most Read