Energy Minister Bill Bennett

Site C dam construction to start next summer

Province to take less revenue from BC Hydro to minimize its debt, says $8 billion project is the cheapest available option to meet demand

The B.C. government has given the go-ahead for BC Hydro to start construction on a third dam on the Peace River, with a delay of six months to try to work out settlements with area aboriginal communities and landowners whose properties will be flooded or cut off.

Energy Minister Bill Bennett said Tuesday an update of the construction costs upheld the $7.9 billion estimate for the Site C dam that was developed in 2010, but the estimate has risen.

Delaying the project six months from its original start date adds inflation and interest costs, and calculating the effect of the provincial sales tax replacing the HST bringing the total to $8.34 billion, and the province is establishing a “project reserve” of $440 million to bring the total estimated cost to $8.77 billion.

The project reserve is in case of unforeseen events such as a rise interest rates during the eight-year construction period.

BC Hydro CEO Jessica McDonald said the six-month delay provides time to work out agreements with Treaty 8 First Nations who have declined settlement offers. The federal-provincial environmental review panel gave the go-ahead for the project in May, but noted its unavoidable impacts on aboriginal hunting, fishing and trapping rights that are assured by the 1899 treaty.

A group of Peace valley landowners has already started legal action against the project, having refused offers from BC Hydro to buy their land. Aboriginal groups in Alberta, downstream of the project, have also started court action against it.

NDP leader John Horgan called the decision “a $9 billion gamble” and repeated his call for a review by the B.C. Utilities Commission to see if the additional power is going to be needed by the time the dam is operating in 2025.

The BCUC will determine BC Hydro rates in the years ahead, and how much they will go up to pay for the most expensive public construction project in B.C. history. The government plans to mitigate BC Hydro rate impact by reducing the dividend the government takes from the power company’s operations each year.

Bennett said a review of alternative clean energy sources, including wind, solar and geothermal power, showed they can’t compete on price because they are intermittent sources that would require backup power.

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

PHOTOS: B.C. Day long weekend on White Rock beach

Hundreds of families gathered at the beach Sunday

Seeds of Change Surrey to launch two new programs

United Way of the Lower Mainland donated $77,000

White Rock RCMP to host free bicycle registration clinic

Stolen registered bicycles are easier to return to proper owner if recovered

White Rock Concerts subscription series plans to weather pandemic

The White Rock Concerts series cancelled its 2020-21 season due the uncertainty of health risks

VIDEO: Otter pups learn to swim at B.C. wildlife rescue facility

Watch Critter Care’s Nathan Wagstaffe help seven young otters go for their first dip

Plane crashes into Nelson supermarket parking lot

Pilot and passenger have minor injuries

Michael Buble among 13 British Columbians to receive Order of B.C.

Ceremony will be delayed to 2021 due to COVID-19

U.S. border communities feel loss of Canadian tourists, shoppers and friends

Restrictions on non-essential travel across the Canada-U.S. border have been in place since March 2`

Rollout of COVID-19 Alert app faces criticism over accessibility

App requires users to have Apple or Android phones made in the last five years, and a relatively new operating system

Fraser Valley Bandits clinch playoff spot with win

Bandits down Niagara River Lions 70-57 on Sunday, improve to 3-2

Alleged impaired driver sparks small wildfire near Lytton after crash: B.C. RCMP

Good Samaritans prevented the blaze from getting out of control

B.C. First Nation adopts ‘digital twinning’ software to better manage territory

Software allows users to visualize what a mountain might look like if the trees on its slopes were logged

Most Read

l -->