Newly-released plans show an elevated 16-kilometre SkyTrain line from Surrey to Langley. (TransLink)

TransLink reveals new plans for proposed Surrey-Langley SkyTrain

No cost estimates, but the Fraser Highway line is expected to open by 2025

Despite concerns over delayed construction after Metro Vancouver mayors’ opted for SkyTrain over light rail, TransLink plans show the agency intends to finish its South of the Fraser rail plans just one year behind schedule.

TransLink and the Mayors’ Council on Regional Transportation had long planned for light rail in Surrey and along the Fraser Highway to Langley.

The $1.65 billion Surrey-Newton-Guildford portion was scheduled to start operations in 2024 but those plans were thrown out after newly-elected Surrey Mayor Doug McCallum convinced the Mayors’ Council to look at SkyTrain instead.

READ MORE: Surrey council unanimously passes motion to ‘cancel ’ LRT

READ MORE: Metro Vancouver mayors cancel Surrey LRT in favour of SkyTrain

Newly-posted draft SkyTrain plans from TransLink show how the agency plans to convert over to a SkyTrain line along Fraser Highway and enhance B-Line service in the Surrey-Newton-Guildford area.

A TransLink spokesperson confirmed the 2025 completion date was for spending the $1.65 billion already set aside for light rail in Surrey-Newton-Guildford.

The available funding will push SkyTrain further into Surrey along Fraser Highway, but will not be sufficient to extend the line all the way to Langley.

Although TransLink says the $1.65 billion in funding for light rail will likely transfer over to SkyTrain, much of that money comes from senior government and the agency will have to submit a new business case in order to transfer it to a different form of rail.

Newly-posted draft SkyTrain plans from TransLink show that the agency plans on completing at least the Surrey portion of the 16 kilometre SkyTrain line from Surrey to Langley by 2025, just one year after the Surrey-Newton-Guildford light rail line was scheduled to be completed.

TransLink plans show a proposed completion date of 2025 for Surrey to Langley SkyTrain along Fraser Highway. (TransLink)

The plans do not include a cost estimate for the new SkyTrain line but the agency currently has $30 million set aside for “pre-design work” in 2019. Light rail along Fraser Highway was estimated to cost $1.9 billion, while SkyTrain was forecasted to come in at $2.9 billion.

As of December, TransLink says it has spent $56.6 million on light rail, down from a $77 million estimate the month prior.

READ MORE: TransLink CEO weighs in on Surrey’s move from LRT to SkyTrain

READ MORE: Fleetwood BIA comes out swinging against SkyTrain, releases renderings

All planned 27 kilometres of South of the Fraser rapid transit are expected to cost $3.5 billion.

However, McCallum has said he believes SkyTrain could be built for nearly the same cost as previously-planned light rail.

The new proposal would see the cancellation of planned B-Lines along Fraser Highway, that were supposed to serve as a “prelude to rail” and start running in 2019.

READ MORE: TransLink to roll out four B-Lines as ‘prelude to rail’ by 2019

Instead, TransLink would “develop a new service plan” that addresses “overcrowding and improves service quality” along Fraser Highway.

The agency notes that public consultation may be needed before it proceeds with “cost-effective” transit plans for that corridor, in order to build ridership before SkyTrain comes in.

It recommends some funding be set aside to upgrade the 96 B-Line for the Surrey-Newton-Guildford area, as it will no longer be getting light rail service.

READ MORE: McCallum says Trudeau ‘supportive’ of Surrey SkyTrain plans, local police force

An alignment concept summary from TransLink shows the Fraser Highway SkyTrain would be elevated, despite previous statements from McCallum that the line could be more cheaply completed at ground level.

The 16-kilometre line would connect to the end of the Expo Line at King George Station and include eight new stations at first, with plans for another one later on, and bus exchanges at Willowbrook and Langley Centre. There is no completion date set for the Langley portion of the line.

It would require 55 new SkyTrain cars.

TransLink’s proposal will be presented to the Mayors’ Council at their Dec. 13 meeting.


@katslepian

katya.slepian@bpdigital.ca

Like us on Facebook and follow us on Twitter.

Editor’s note: A previous version of this story said the SkyTrain line would be extended all the way to Langley by 2025. TransLink has clarified that the $1.65 billion set aside for light rail would only extend the line further into Surrey by 2025.

Just Posted

Rugged wheelchair rolled out at Crescent Beach

Accessibility of popular South Surrey waterfront boosted

B.C. serves up $6.3 million boost to province’s respite program

The announcement, in Surrey, aims to give parents of special needs children a break

Schedule released for South Surrey-hosted Americas Olympic Softball Qualifier

Canadian national women’s fastpitch team to open tournament against Cuba

Biting and jumping are paw-sitives when raising a police dog puppy

18-week-old Maya is training with Delta police to one day take a bite out of crime

South Surrey golfer qualifies for U.S. Women’s Amateur Championship

Earl Marriott Secondary student Lauren Kim, 13, to tee off at prestigious event in Mississippi

Feds lowered poverty line, reducing the number of seniors in need: documents

Liberals introduced a poverty line that was below the prior low-income cutoff

$900M settlement reached in class action on sexual misconduct in Canadian military

After facing criticism, the government moved to begin settlement proceedings in early 2018

Tax take stays ahead of increased B.C. government spending

Tax revenue $2.1 billion higher than budget in 2018-19

Two toddler siblings found drowned on First Nation in Alberta

The Siblings were found drowned on their family’s property, according to RCMP

Chiefs honour Indigenous leader wrongfully hanged in B.C. 154 years ago today

Chief Joe Alphonse says they want his remains returned to his homeland in B.C.’s Cariboo region

Rare white ravens spotted again on Vancouver Island

Nature photographer Mike Yip said mysterious birds back in Coombs area

B.C. government seeks advice on reviving Interior forest industry

Public website opens as meetings start with community leaders

RCMP use helicopter and police dog to search for suspect on Sts’ailes First Nation

Small reserve near Agassiz surrounded by police vehicles, helicopter, ERT

Missing Vancouver Island woman believed to be on mainland

Rhonda Stevenson, 43, last seen July 13 in central Nanaimo

Most Read

l -->