Powerhouse and water intakes under construction at Site C dam project in northeast B.C., spring 2019. (B.C. Hydro)

B.C. Indigenous group vows to battle Site C dam in court again

B.C. Hydro project preparing to divert Peace River next summer

He has lost at every level of Canada’s court system, but the West Moberly First Nations chief is vowing to go to court again in an effort to stop completion of the Site C dam in northeastern B.C.

A lawyer for Chief Roland Willson issued a statement Tuesday saying discussions with the B.C. government to avoid the latest legal action against the dam have ended, and a trial is expected to begin in March 2022 to determine if West Moberly’s treaty rights have been infringed by construction of the third dam on the Peace River near Fort St. John.

Willson and his lawyer Tim Thielmann quoted Premier John Horgan’s statements while B.C. opposition leader in support of traditional hunting and fishing rights under Treaty 8, the 1899 treaty in which the region’s first nations ceded the territory to the Crown.

“We can’t disclose anything confidential from the discussions with B.C., but I can assure you that there are dark days ahead for Site C,” Willson said, predicting further construction delays.

B.C. Hydro postponed the diversion of the river for construction of the earth-fill dam until the summer of 2020, but said the delay wouldn’t mean missing the 2024 target for the dam to begin producing power. That delay and other unforeseen construction issues prompted the provincially owned utility to increase its cost estimate from $8.5 billion to $10.7 billion.

RELATED: 15th court action dismissed against Site C dam

RELATED: NDP proceeds with Site C dam, cost up to $10.7B

Horgan and Energy Minister Michelle Mungall inherited the project from former premier Christy Clark, who took an active role in pushing for its completion after her predecessor Gordon Campbell made the decision to proceed. The Horgan government reluctantly approved carrying on with Site C after forming a minority government in 2017.

The project has thousands of workers on site this summer, completing river diversion tunnels and building the powerhouse, intakes and other key components. As the third dam, Site C reuses stored water from the Peace Canyon and W.A.C. Bennett dams upstream, producing enough power for 450,000 homes with a much smaller reservoir size.

West Moberly and the Prophet River First Nation have carried on a long legal battle against Site C, which will flood more than 80 km of valley bottom land, widening and deepening the river. Their challenge of provincial permits was rejected by the B.C. Supreme Court in 2016, and later by the Federal Court of Appeal. The Supreme Court of Canada declined to hear the last appeals of that case in 2017.

In 2006, Campbell’s government and B.C. Hydro negotiated compensation of $14 million with ongoing support payments for the communities of Kwadacha and Tse Keh Dene, established at new sites on Williston Reservoir after original reserves were flooded by the original W.A.C. Bennett dam in 1967.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

VIDEO: Surrey RCMP supporters make noise during rally outside city hall

‘Keep the RCMP in Surrey’ leader Ivan Scott says municipal force ‘not a done deal’

International South Asian expo pitched for Surrey’s Bear Creek Park

Mayor Doug McCallum says the idea ‘shows a lot of promise’

White Rock council declares disapproval of ride-hailing rules

City to submit resolution to UBCM, send letter to B.C. Passenger Transportation Board

Sikh millworker lodges human rights complaint against Interfor, again

Mander Sohal, fired from Delta’s Acorn Mill, alleges discrimination based on religion and disability

Developer offers free Tesla 3 with purchase of South Surrey townhome

Century Group’s offer for Viridian development runs through Oct. 31

VIDEO: Liberals make child care pledge, Greens unveil platform on Day 6 of campaign

Green party leader Elizabeth May unveils her party’s platform in Toronto

Canucks sign Brock Boeser to three-year, US$17.6-million deal

Young sniper will be in Vancouver Tuesday

B.C. forest industry looks to a high-technology future

Restructuring similar to Europe 15 years ago, executive says

RCMP conclude investigation into 2017 Elephant Hill wildfire

Files have been turned over to BC Prosecution Service

B.C. wants to be part of global resolution in opioid company bankruptcy claim

Government says settlement must include Canadian claims for devastation created by overdose crisis

Vancouver police officer hit with bear spray mid-arrest

Officer had been trying to arrest a woman wanted province-wide

B.C. ends ‘birth alerts’ in child welfare cases

‘Social service workers will no longer share information about expectant parents without consent’

U.S. student, killed in Bamfield bus crash, remembered as ‘kind, intelligent, talented’

John Geerdes, 18, was one of two UVic students killed in the crash on Friday night

B.C. communities urged to improve access for disabled people

One in four B.C. residents has disability, most want to work

Most Read

l -->