Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC HydroBC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

South Surrey-based pen-pal program aims to reduce seniors’ isolation during pandemic

South Surrey/White Rock concierge service to connects kids & seniors virtually

Surrey city council moving to virtual meetings

For public hearings, people can register to speak via telephone

‘An extra $220 every 90 days’: B.C. patients pay more dispensing fees due to prescription limits

Kelowna woman says it’s outrageous to charge for refills every 30 days

33-storey highrise proposal coming to Surrey council, first of three phases

Second and third phases include 36-storey and 31-storey towers

COVID-19: Daily update on the pandemic in Surrey, White Rock, Delta and beyond

APRIL 4: Two people in Delta fined for trying to re-sell N95 masks

‘Hold our line’: 29 new cases of COVID-19 announced in B.C.

Saturday’s number of new cases marks the lowest in weeks.

Exercises move online with YMCA’s new nationwide virtual workout program

YThrive Home offers dozens of free workout videos for people during COVID-19 self-isolation period

Two inmates found positive for COVID-19 at Mission Institution; two other tests pending

15 staff self-isolating waiting results, says correctional officer

B.C. community service provider hosts friendly art competition for youth

Theme for Pacific Community Resources contest is ‘finding the silver lining in difficult times’

Critic, workers’ group ‘disappointed’ Trudeau chose Amazon to distribute PPE

Amazon Canada said in an email to The Canadian Press that it is working with Canada Post, Purolator

Full World COVID-19 update: National Guard collect ventilators in New York; Spain, Italy improve

Comprehensive coronavirus update with news from around the world.

TransLink to reduce service on some bus routes, SeaBus, West Coast Express

Changes start April 6 ‘due to low ridership and financial pressures’ amid COVID-19

Most Read

l -->