Tour de White Rock, other events still on, despite waterfront delays

City staff hopeful Memorial Park could be half complete by Canada Day

City of White Rock staff are hopeful that work on the Memorial Park upgrade at the waterfront can be completed at least halfway by Canada Day.

But that’s not likely to include the staircase down to the pier or rebuilding of the washrooms, according to chief administrative officer Dan Bottrill, and staff are also assembling back-up plans for shifting select popular summertime events to East Beach for this year.

“We’ve done some non-destructive work at the site and the archeological-impact assessment is continuing,” he told Peace Arch News last week.

“As we expected, the archeological impact work is turning up nothing – it’s just fill.”

Work, which began in September, was suspended as a result of a cease-and-desist order from Semiahmoo First Nation, who cited inadequate consultation over plans for the site, considered ancestral SFN territory, and called for an archeological-impact assessment.

“At this point, we’re reworking the schedule with our construction company to try to figure out what we’re looking at,” Bottrill said. “We’re hopeful we can still hit the July 1 target for the western portion of the plan, which is mainly the landscaping and the plaza area. But the washrooms and staircase and the other patio on the eastern side are going to to take more time.”

Recreation and culture director Eric Stepura told PAN that, minus a firm date on completion of the phases of work, his staff is working out alternative plans for Canada Day by the Bay, the TD Concerts at the Pier series and August long-weekend Sea Festival, “and, possibly, other events.”

“We’re thinking in terms in terms of relocating the main stage to the parking lot just east of Totem Park plaza – that’s our back-up plan in case Memorial Park is not ready in time,” Stepura said.

Bottrill also said there was no intention to relocate the annual Tour de White Rock cycling road race, scheduled for July 14 and 15, off Marine Drive.

“Absolutely not,” he told PAN. “That’s an elite event in White Rock that has been going on for many, many years and we’re not going to mess with that. We would be taking that event into consideration with any kind of work we did near the roadway. There’s no way we are messing with that.”

The Picnic on the Pier fundraiser for the Peace Arch Hospital Foundation co-ordinated by Landmark Premiere Properties – which raised more than $56,000 in its second year in 2017 –is usually scheduled for the waterfront on a week night in the second week of August.

Foundation public relations director Vicki Brydon said that, in light of Memorial Park construction, access to the pier, wheelchair accessibility and washroom availability would be key logistical challenges for the event, but said she is optimistic that it can still go forward this year.

“We’re very motivated to work with the city to find solutions so that Picnic on the Pier 2018 can be a reality,” she said.

The Memorial Park project – budgeted at some $5.5 million in total – is planned to provide a new flexible plaza space, public art, amphitheatre seating, built-in lighting, enlarged washrooms, a children’s water-spray pad and a wider promenade in the area, which reaches from the east side of the Mueseum and Archives to the current parking lot to the east of the existing washrooms.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Lefeuvre Road, near Myrtle Avenue, was blocked to traffic on Thursday (Dec. 3) after an abandoned pickup truck was found on fire. Police are investigating to determine if there are any links to a killing an hour earlier in Surrey. (Shane MacKichan photo)
Torched truck found in Abbotsford an hour after killing in Surrey

Police still investigating to determine if incidents are linked

Surrey Pretrial in Newton. (Photo: Tom Zytaruk)
Surrey Pretrial hit with human rights complaint over mattress

The inmate who lodged the complaint said he needed a second mattress to help him manage his arthritis

Clockwise from top left: Karen and Otto Froelich; Karen and Judy Reefschlager; Reefschlager and Karen Froelich celebrate the 25th annivesary of Northcrest Care Centre (Contributed photos)
White Rock trio recognized for being ‘pioneers in seniors’ care’

Karen and Otto Froelich and Judy Reefschlager honoured by BC Care Providers Association

Kyle Mclauchlin with his nephew, Cassius, in a photo posted to the “Kyle Mclauchlin’s road to recovery” page on gofundme.com.
Train crushes foot of Surrey man whose brother was first on the scene to help

‘We are just trying to be with him to keep him calm,” Fraser Mclauchlin says of injured sibling, Kyle

A coal-fired power plant seen through dense smog from the window of an electric bullet train south of Beijing, December 2016. China has continued to increase thermal coal production and power generation, adding to greenhouse gas emissions that are already the world’s largest. (Tom Fletcher/Black Press)
LNG featured at B.C. energy industry, climate change conference

Hydrogen, nuclear, carbon capture needed for Canada’s net-zero goal

People line up at a COVID-19 assessment centre during the COVID-19 pandemic in Scarborough, Ont., on Wednesday, December 2, 2020. Toronto and Peel region continue to be in lockdown. THE CANADIAN PRESS/Nathan Denette
COVID-19 vaccine approval could be days away as pressures mount on health-care system

Many health officials in regions across the country have reported increasing pressures on hospitals

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

(Needpix.com)
Pandemic has ‘exacerbated’ concerns for B.C. children and youth with special needs: report

Pandemic worsened an already patchwork system, representative says

Janet Austin, the lieutenant-governor of British Columbia, not seen, swears in Premier John Horgan during a virtual swearing in ceremony in Victoria, Thursday, Nov. 26, 2020. Horgan says he will look to fill gaps in the federal government’s sick-pay benefits program aimed at preventing the spread of COVID-19. THE CANADIAN PRESS/Jonathan Hayward
B.C. premier says province prepared to patch holes in new federal sick-pay benefits

Horgan said workers should not be denied pay when they are preventing COVID-19’s spread

Provincial health officer Dr. Bonnie Henry updates B.C.’s coronavirus situation at the legislature, Nov. 30, 2020. (B.C. government)
Hockey team brought COVID-19 back from Alberta, B.C. doctor says

Dr. Bonnie Henry pleads for out-of-province travel to stop

Most Read